SAFETY & QUALITY / DOCUMENTATION

Zero recordable incidents across 38 consecutive civil works projects — audited, multi-year, Hokkaido-proven.

Between 2017 and 2024, Kenchan Construction Group completed 38 heavy civil contracts without a single lost-time injury. The record is audited annually by the Japan Construction Occupational Safety and Health Association and forms the baseline of every project safety plan we submit with an RFQ.

  • 0.00TRIR · 2017–2024
  • 38Consecutive Projects
  • 312FTE Field Personnel
  • 1,217Completed Contracts

§ 02 — THIRD-PARTY VERIFICATION

Audited and certified by the bodies that pre-qualify heavy civil contractors.

Procurement evaluators can cross-check every safety, quality, and financial credential against a named registrar. No self-attestation.

OCCUPATIONAL SAFETY

JCOSHA Annual Audit

Japan Construction Occupational Safety and Health Association audits every active Kenchan project annually. The 0.00 TRIR record across 38 consecutive projects (2017–2024) is drawn from these audit reports.

Auditor
JCOSHA
Cycle
Annual, site-level
Scope
All active contracts

QUALITY MANAGEMENT

ISO 9001:2015

Certified since 2004. Covers earthworks, structural steel erection, concrete placement, pile foundations, and project management — the 92% of work scope Kenchan self-performs.

Standard
ISO 9001:2015
Certified
2004–present
Scope
Civil & industrial construction

ENVIRONMENTAL MANAGEMENT

ISO 14001:2015

Certified since 2011. Underwrites the SBTi-aligned roadmap to a 42% Scope 1+2 emissions reduction by FY2030 versus the FY2019 baseline.

Standard
ISO 14001:2015
Certified
2011–present
Target
−42% Scope 1+2 by FY2030

FINANCIAL STRENGTH

JCR A− Credit Rating

Japan Credit Rating Agency, Ltd. reaffirmed an A− rating in March 2024. Audited financial statements available for the past 38 years across 1,200+ completed contracts with zero bond claims.

Agency
JCR, Ltd.
Rating
A− (reaffirmed Mar 2024)
Bond Claims
Zero, 1,217 contracts

§ 03 — METHODOLOGY

The cold-weather concrete pouring protocol that lets us pour when other contractors demobilize.

In 2019, the Hokkaido Branch of the Japan Civil Engineering Contractors' Association formally adopted a cold-weather concrete pouring protocol co-developed and field-proven by Kenchan. It is the document that makes a January bridge-deck pour possible in Otaru.

  1. 01

    Pre-pour thermal modeling

    Hydration heat curves are modeled against the 7-day Hokkaido forecast for the pour footprint. Mix design, cement content, and accelerator dosage are tuned to maintain a core temperature >5°C for the first 72 hours.

  2. 02

    Aggregate pre-heating at source

    Sand and coarse aggregate are pre-heated in the Otaru batch plant before transit. Incoming concrete temperature at the placement face is documented in real time and rejected below the 10°C threshold.

  3. 03

    Enclosure and heated curing

    Forms are wrapped in insulated tarpaulins with monitored forced-air heat. Internal concrete temperature and ambient differential are logged at 30-minute intervals for the first 168 hours.

  4. 04

    Strength verification before formstrip

    Field-cured cylinders and maturity-meter readings must reach the specified compressive strength before formstripping. Stripping decisions are signed off by a licensed 1-kyu construction engineer, not the foreman.

OUTCOME — sub-zero pours delivered on critical path, with the field-cure strength record preserved in the as-built documentation handed to the client at handover.

§ 04 — RECURRING SAFETY CYCLE

The system behind the 0.00 TRIR.

A zero-incident record is not a streak. It is the output of a four-stage cadence repeated on every project, every day, every year.

  1. 01

    Pre-mobilization engineering

    Project-specific risk assessment, method statements, and lift studies prepared by the in-house engineering team before a machine leaves the yard.

    Owner: Engineering Manager

  2. 02

    Site induction & daily toolbox

    Every worker and visitor receives a documented site induction before stepping on the workface. Toolbox talks run at 07:00 every working day.

    Owner: Site Safety Officer

  3. 03

    JCOSHA annual audit

    External auditors from JCOSHA inspect every active project once per year. Findings, corrective actions, and close-out dates are logged in the project file.

    Owner: Third-party (JCOSHA)

  4. 04

    Executive quarterly review

    Kenchan's executive committee reviews lagging indicators (TRIR, near-miss reports, audit findings) and leading indicators (training hours, observation cards) once per quarter.

    Owner: President / Executive Committee

§ 05 — PRE-QUALIFICATION METRICS

The four numbers a procurement officer writes down first.

0.00TRIR

Total Recordable Incident Rate, 38 consecutive civil works projects (2017–2024). JCOSHA-audited.

38PROJECTS

Consecutive heavy civil and industrial contracts completed without a lost-time injury.

96% RETENTION

Year-over-year field crew retention. Average employee tenure across the workforce: 14.6 years.

1,217CONTRACTS

Completed construction contracts since incorporation. Cumulative contract value exceeding ¥84 billion.

§ 06 — PRE-RFQ DUE DILIGENCE

Questions an MLIT or general-contractor evaluator raises before opening the form.

If your evaluator's question is not here, send it to [email protected]. We respond inside one working day.

Has Kenchan recorded any fatalities or life-altering incidents in the past ten years?

No. The publicly disclosable safety record covering 2014 through 2024 shows zero fatalities and zero life-altering incidents. The 0.00 TRIR (Total Recordable Incident Rate) covers the 38 consecutive civil works projects delivered between 2017 and 2024 and is the figure referenced in our pre-qualification submissions.

Can a procurement officer audit the JCOSHA reports directly?

Yes. Audit reports are released to the client or to a nominated third-party evaluator under NDA at the RFQ stage. Redacted summaries citing the auditor, the project, and the close-out date can be provided without NDA during the pre-qualification exchange.

What insurance cover does Kenchan carry, and at what limit?

Kenchan carries contractors' all-risk (CAR) and third-party liability insurance with limits scaled to the contract value, plus statutory workers' compensation cover under Japanese labour law. Specific limits, named insurers, and certificates of currency are released with the tender documents.

Will Kenchan mobilize outside Hokkaido, Aomori, and northern Tohoku?

No. Kenchan does not mobilize outside Hokkaido, Aomori, and northern Tohoku. The Otaru batch plant, the quarry, the 142-machine fleet, and the 312-person workforce are configured around this operating footprint. RFQs outside that geography are returned with a referral to a partner contractor.

How much of the work scope is subcontracted versus self-performed?

Kenchan self-performs 92% of the work scope — earthworks, structural steel erection, concrete placement, and pile foundations. Sub-tier engagement is limited to specialist trades outside that envelope (e.g. specialist cathodic protection, niche instrumentation). The full sub-tier register and pre-qualification status of each named sub-tier is provided with the tender.

Ready to open an RFQ conversation? Send the project brief and we will return a documented response.